Table 2: Timeline for project implementation.

Phase

Milestones

Timeframe

1

Pre-implementation EMR Chart review

1-2 weeks

2

Announcement of the DNP project, Asthma Protocol to staff

1 week

3

In-service to providers and clinical staff. Begin using the Asthma Protocol

2-3 weeks

4

Post-implementation EMR chart review

1-2 weeks